shangshi
Your present location:
Home
>>
>>
>>
Puan project 2×660MW project #1 unit boiler pipe blowing was successfully completed
NEWS

Puan project 2×660MW project #1 unit boiler pipe blowing was successfully completed

  • Categories:Industry news
  • Author:
  • Origin:
  • Time of issue:2021-07-22 19:36
  • Views:

(Summary description)On January 2, the boiler blowing of the 2×660MW project #1 unit of the Pu'an project was successfully completed. This was the realization of another major milestone after boiler water pressure and boi

Puan project 2×660MW project #1 unit boiler pipe blowing was successfully completed

(Summary description)On January 2, the boiler blowing of the 2×660MW project #1 unit of the Pu'an project was successfully completed. This was the realization of another major milestone after boiler water pressure and boi

  • Categories:Industry news
  • Author:
  • Origin:
  • Time of issue:2021-07-22 19:36
  • Views:
Information

On January 2, the boiler blowing of the 2×660MW project #1 unit of the Pu'an project was successfully completed. This was the realization of another major milestone after boiler water pressure and boiler pickling. The realization of this goal directly paved the way for the start-up of the entire set of turbines, and also laid a solid foundation for the commissioning of unit #1 for power generation.

RELEVANT NEWS

Zhoukou

Zhoukou Gas Power Plant Project Unit 1 steam turbine cover was successfully completed

At 19:28 on January 2, the buckle cover for the steam turbine of Unit 1 of the Zhoukou Gas Power Plant Project undertaken by Henan Engineering Company was successfully completed. The construction node
2021-07-22
Puan

Puan project 2×660MW project #1 unit boiler pipe blowing was successfully completed

On January 2, the boiler blowing of the 2×660MW project #1 unit of the Pu'an project was successfully completed. This was the realization of another major milestone after boiler water pressure and boi
2021-07-22
Shaaneng

Shaaneng Zhaoshipan Coal-Power Integration Project Leilongwan Power Plant (2×1000MW) Project #1 cooling tower crane was successfully demolished

At 15:30 on January 2nd, the Shaaneng Zhaoshipan Coal and Electricity Integration Project Leilongwan Power Plant (2×1000MW) Project #1 cooling tower QTZ (TCT7527-20) type undertaken by Anhui Electric
2021-07-22
Hoisting

Hoisting of the deaerator for Unit 2 of Huaneng Yantai Bajiao Power Plant Project Department was completed

At noon on January 2, the deaerator for Unit 2 of the Huaneng Yantai Bajiao Power Plant Project Department contracted by Anhui Electric Power Construction First Engineering Co., Ltd. was completed. Th
2021-07-22
上一页
1
2
3
shangshi

页脚联系我们

Time of issue:2021-07-20 11:41:29
Fax: +86(021)52287326
CopyRight © 2021 shangshi high-speed turbo power all rights rerserved