Summary of thermal power projects approved, won bids, and started in one week (1.1-1.5)
NEWS

Summary of thermal power projects approved, won bids, and started in one week (1.1-1.5)

  • Categories:Industry news
  • Author:
  • Origin:
  • Time of issue:2021-07-22 19:35
  • Views:

(Summary description)Polaris Thermal Power Network has compiled the thermal power projects during the week from January 1, 2018 to January 5, 2018: involving start of construction, grid connection, environmental assessmen

Summary of thermal power projects approved, won bids, and started in one week (1.1-1.5)

(Summary description)Polaris Thermal Power Network has compiled the thermal power projects during the week from January 1, 2018 to January 5, 2018: involving start of construction, grid connection, environmental assessmen

  • Categories:Industry news
  • Author:
  • Origin:
  • Time of issue:2021-07-22 19:35
  • Views:
Information
Polaris Thermal Power Network has compiled the thermal power projects during the week from January 1, 2018 to January 5, 2018: involving start of construction, grid connection, environmental assessment and acceptance, etc.

RELEVANT NEWS

Zhoukou

Zhoukou Gas Power Plant Project Unit 1 steam turbine cover was successfully completed

At 19:28 on January 2, the buckle cover for the steam turbine of Unit 1 of the Zhoukou Gas Power Plant Project undertaken by Henan Engineering Company was successfully completed. The construction node
2021-07-22
Puan

Puan project 2×660MW project #1 unit boiler pipe blowing was successfully completed

On January 2, the boiler blowing of the 2×660MW project #1 unit of the Pu'an project was successfully completed. This was the realization of another major milestone after boiler water pressure and boi
2021-07-22
Shaaneng

Shaaneng Zhaoshipan Coal-Power Integration Project Leilongwan Power Plant (2×1000MW) Project #1 cooling tower crane was successfully demolished

At 15:30 on January 2nd, the Shaaneng Zhaoshipan Coal and Electricity Integration Project Leilongwan Power Plant (2×1000MW) Project #1 cooling tower QTZ (TCT7527-20) type undertaken by Anhui Electric
2021-07-22
Hoisting

Hoisting of the deaerator for Unit 2 of Huaneng Yantai Bajiao Power Plant Project Department was completed

At noon on January 2, the deaerator for Unit 2 of the Huaneng Yantai Bajiao Power Plant Project Department contracted by Anhui Electric Power Construction First Engineering Co., Ltd. was completed. Th